Admiralty Court Louise Glover Admiralty Court Louise Glover

Alize 1954 & Anor v Allianz Elementar Versicherungs AG & Ors [2019]

“Following a grounding on leaving a port, cargo interests contested Owners' claim for GA and salvage contribution. The Court found that Owners' passage plan was defective and the Master's decision to leave the fairway was imprudent. The former was held to be the operative cause, such that the Vessel was unseaworthy pursuant to Art. III r.1., depriving the Owners of an Art. IV r. 2 (a) defence and their claim to contribution. Although irrelevant to the outcome, the Judge dismissed cargo interests' argument that following "Volcafe", the burden of dis-proving causative unseaworthiness under Art. III r.1 lay on the carrier, stating that in his judgment, that decision was restricted to Art. III r.2.”

Read More
Arbitration Louise Glover Arbitration Louise Glover

London Arbitration 6/19

“The performance clause in a trip time charter (South Africa to China) defined good weather as "wind speeds of maximum beaufort force 4 (11-16knots) and total-combined (sea and swell) significant wave height confined to limits of douglas sea state 3 (0.5-1.25 meters)". Despite acknowledging the uncertainty of the terminology and the difficulty in reconciling two entirely different measures of sea condition, the Tribunal found that there would be no contradiction if good weather criteria were restricted to significant wave heights of no more than 1.25 m, even though this might render DSS3 surplusage and lower the required performance standard to something less than might be expected in charters of this nature.”

Read More
Commercial Court Louise Glover Commercial Court Louise Glover

Silverburn Shipping (loM) Ltd v Ark Shipping Company LLC (M/V "ARCTIC") [2019]

“The High Court held that the Classification clause (9) in a BARECON '89 Charterparty is both an absolute obligation and a condition, such that if charterers allow Class to lapse, owners are entitled to terminate. In so doing it overturned an arbitration award concluding that clause (9) was part of the continuing maintenance obligation and imposed only an intermediate obligation of reasonable diligence, i.e. to reinstate the vessel's Class within a reasonable time.”

Read More
Admiralty Court Louise Glover Admiralty Court Louise Glover

Nautical Challenge Ltd v Evergreen Marine (UK) Ltd [2019]

“Last year the Court of Appeal ruled that responsibility for the collision between Alexandra I (container ship) and Eversmart (tanker) was to be apportioned 80:20. The claims totalled some USD36m. The Admiralty Court recently assessed recoverable damages at USD9.3m for Alexandra I and USD2.53 for Eversmart. The Court declined to award extended loss to Alexandra I on the basis of "impecuniosity" of her Owners (said to cause delay to repairs, causing loss of market and eventual judicial sale). The owners had failed on the facts to establish the necessary causation between collision and delay/market collapse.”

Read More
Commercial Court Louise Glover Commercial Court Louise Glover

HSBC Bank Plc v Pearl Corporation SA & Ors [2019]

“HSBC advanced USD3Om for the acquisition of 2 vessels. A subsequent fall in the freight market resulted in the owning entities being in breach of the financing arrangements. The Bank sought to enforce its claim under the personal guarantees (which were subject to English jurisdiction but Greek law). The guarantor argued that the Bank's conduct had been contrary to a principle of "good faith" enshrined in Greek law. The High Court found that the allegations against the Bank — including a) failing to compromise with borrowers b) taking time to negotiate debt restructuring, c) refusing a 'haircut' to the debtor and d) preferring one customer to another — were not made out and that the Bank's claim succeeded in full.”

Read More
Arbitration Louise Glover Arbitration Louise Glover

London Arbitration 4/19 — [2019]

“The incorporation of the ICA in a time charterparty meant that both parties agreed to the definition of "cargo claims" as "claims for loss, damage, shortage...overcarriage of or delay to cargo". A tribunal considered that there was no reason to give a different meaning to those words elsewhere in the charterparty, including an addendum clause rendering Charterers fully liable for all "cargo claims". Unsuccessfully, Charterers argued that a claim for diminution in value of the cargo due to the vessel's delay fell outside the meaning of the addendum clause.”